October 2020 News
2 December 20- Operations related to buildings and facilities in the +1 to +5 floors are underway.- The total progress in the +1 and +2 classes is about 77%.- The total progress in the +3 to +5...
- Operations related to buildings and facilities in the +1 to +5 floors are underway.- The total progress in the +1 and +2 classes is about 77%.- The total progress in the +3 to +5...
- 95% progress in the construction of four engine room chillers by Sari Pouya Company- Concluding a contract with Mehr Fakhr Company to supply and supply 57 elevators with the Otbis China brand.- Preparing and...
- Execution of 400 units in the facade equivalent to 2000 square meters- Execution of operations of buildings and facilities in floors +1 to +5- Holding HSE meetings- Holding weekly and continuous meetings with contractors-...
- Organizing engineering meetings virtually to review plans- Pursuing the supply of electricity to the project through the supply contractor and requesting to prepare final supply plans for the project- Following up with the official...
- Organizing regular engineering meetings to review plans and sequence of executive tasks- Organizing regular weekly meetings of the employer and contractors regarding the work process and reviewing obstacles and problems and the executive schedule-...
Organize weekly engineering meetings to review deficiencies and deficits and respond to the workshop executive contractorWeekly project control meetingsReviewing the progress of physical operations in the weekly meetings of the employer and the contractor with...